 Completed Projects 
1- Construction of Sout Pars Gas Field Phase 12
 Refineries Flares Substructure(EPC) & coastal Protection
  
General Information:
·         Project: Construction of South Pars Gas Field phase 12 Refineries Flares Substructure
·         Location: Asalouyeh, Bushehr Province
·         Employer: Petro Pars Company
·         Consultant: Joint Venture of Karan Darya - Sakoo
·         Contractor: Karan Darya Company
·         Project Duration: 12 months
·         Contract Date: 25/12/2007
·         Primary Expense: 16,315,789 $
 
Technical Information:
·         Core Rock Volume: 506,956 m3
·         Mattress Rock Volume: 38,019 m3
·         Filter Rock Volume: 92,085 m3
·         Toe Rock Volume: 2,597 m3
·         Rock Armour Volume : 75,736 m3
·          Concrete Armour (Accropode Units): 19,000 mincluding 3600 units of 1m& 7700 units of 2m3 Accropode Blocks
 
 
2- Rehabilitation & Reconstruction of C1 & C5
Jetties in Shahid Bahonar Port (EPC)
 
General Information:
·         Project: Rehabilitation & Reconstruction of C1 & C5Jetties in Shahid Bahonar Port
·         Location: Bandar Abbas, Hormozgan Province
·         Employer: National Iranian Oil & Petroleum Distribution Co.
·         EPC Contractor: Karan Darya Co.
·         Assistant Consultant: Hendeseh Pars Consulting Engineers  
·         Implementation Period: 18 months
·         Contract Date: 09/01/2008
·         Expense: 10,516,074 $
 
Technical Information:
·         Pile Driving length: 1708 m, including 52 piles with average penetration length of 30 m.
·         Design & Construction of C1 Jetty Access Bridge: Width of 8 m & length of 60 m, Steel Beams & Concrete slab.
·         Design & Construction of Walkway Truss Bridges: Length of 270 m, tubular sections.
·         Rehabilitation of damaged Concrete Deck & 90 damaged piles of C5 Jetty
·         Design & Construction of 8 Moorings & Rehabilitation of 3 Dolphins
·         Construction & Installation of 8 Bollards and Installation of 6 Fenders, Design of 8 Quick Releases.
·         Design & Construction of Petroleum Installations including Piping, Mechanical, Process & Instrument Systems Considering application of Loading Arms.
·         Design & Construction of Safety & Fire Fighting Systems
·         Design & Construction of Electrical, Control Room & Cathodic Protection Systems
·         Coastal Protection
 
3- Construction of Shahid Haghani Passenger Port
 
General Information:
·         Project: Construction of Shahid Haghani Passenger Port
·         Location: Bandar Abbas, Hormozgan Province
·         Employer: Iranian Ports and shipping organization
·         Consultant: Khak Baft Consulting Engineers  
·         Contractor: Karan Darya Co.
·         Implementation Period: 18 months
·         Contract Date: 5/5/2008
·         Expense: 6,840,950 $
 
Technical Information:
·         Rock (1-900 Kg) Production volume for breakwater: 230,000 m3
·         Rock (900-5000 Kg) Production volume for breakwater: 36300 m3
·         Removal of existing breakwater’s rocks: 13,000 m3
·         Procurement & distribution of gravel behind the Geotextile: 9,000m3
·         Procurement & transportation of S355 steel piles by 600 mm diameter & 14 mm thickness: 200,000 Kg
·         Pile Driving length: 600 m
·         Rebar works: 5,000 Kg
·         In-situ concrete volume: 100 m3
·         Sandblasting & painting by 500 micron thickness: 600 m2
·         Geotextile area: 9,000 m2
·          Dredging volume: 100,000 m3
 
 
4- Land Reclamation of South Pars Gas Field phase 2, Parts 2 & 3
 
General Information:
·         Project: Land Reclamation of South Pars Gas Field Phase 2, Parts 2 & 3
·         Location: South Pars Gas Field, Asalouyeh
·         Employer: Petrochemical Industries Development Management Co.
·         Consultant: Sazepardazi Iran Consulting Engineers Co.
·         Contractor: Karan Darya Co.
·         Duration: 2nd part of phase 2: 21 months. 3rd part of phase 2: 18 months.
·         Contract Date: 2nd part of phase 2: 07/04/2003. 3rd part of phase 2: 20/08/2003.
·         Expense: 28,421,053 $
 
Technical Information:
·         Breakwater Type: Rubble Mound
·         Main breakwater length: 2200 m
·         Jetty Type: Rubble Mound
·         Number of jetties (Access Roads): 7 branches
·         Total Length of Jetties: 2565 m
·         Total area of Basins: 600 hectare
·         Stone material volume: 1,453,000 m3
·         Maximum weight of stone material: 4-9 ton
·         Special weight of stones: 2.65 ton/m3
·         Access road to mine: 60 Km
·         Average distance for transportation of stones: 10 Km from project location
 
 
5- Land Reclamation & Site Preparation of
Petrochemical Areas of Khark Island
 
General Information:
·         Project: Land Reclamation & Site Preparation of Petrochemical Areas of Khark Island
·         Location: Khark Island, Bushehr Province
·         Employer: Petrochemical Industries Development Management Co.
·         Consultant: Sazepardazi Iran Consulting Engineering   
·         Contractor: Karan Darya Co.
·         Implementation Period: 18 months
·         Contract Date: 28/01/2005
·         Expense: 90,568,394 $
 
Technical Information:
·         Soil operation: 1,136,000 m3
·         Excavation: 22,000m3
·         Back filling: 1,068,845m3
·         Soil Transferring: 2,250,000m3
·         Base and Sub Base Volume: 8,000 m3
·         Asphalting: 21,0000 m2/Cm
·         Revetment Volume: 2,000 m3
·         Concrete Volume: 7,000m3
·         Fencing: 2,750m
·         Rebar work: 55,000Kg
 
 
6- Construction of Bandar Abbas Fishing Port Dike & Breakwater
 
General Information:
·         Project: Construction of Bandar Abbas Fishing Port Dike & Breakwater
·         Location: Bandar Abbas, Hormozgan Province
·         Employer: Iran Fisheries Organization
·         Consultant: Sazepardazi Iran Consulting Engineers Co.
·         Contractor: Karan Darya Co.
·         Duration: 30 months
·         Contract Date: 16/11/2003
·         Primary expense: 5,181,297 $
 
Technical Information:
·         Breakwater Type: Rubble Mound
·         Main arm length: 895 m
·         Secondary arm length: 655 m
·         Dike Length: 550 m
·         Basin area: 20 hectare
·         Stone material volume: 460,000 m3
·          Special weight of stones: 2.4 ton/m3
·         Maximum weight of armor: 3,000 Kg
·         Quarry distance: Ghachin Mine within 50Km from the site
 
 
7- Concrete Block Jetty of Bandar Abbas Fishing Port
 
General Information:
·         Project: Concrete Block Jetty of Bandar Abbas Fishing Port
·         Location: Bandar Abbas, Hormozgan Province
·         Employer: Iran Fisheries Organization
·         Consultant: Sazepardazi Iran Consulting Engineers
·         Contractor: Karan Darya Co.
·         Implementation Period: 20 months
·         Contract Date: 04/04/2006
·         Expense: 1,355,769 $
 
Technical Information:
·         Jetty Type: Precast Unreinforced Concrete Blocks
·         Pier Length: Fishing Part: 150m and Commercial Part: 36m
·         Concrete Block Volume: 5,100m3
·         Procurement and installation of Fender: 60 Pieces
·         Rock Material Volume: 37,000m3 of Rocks weighed 100 to 200Kg
·         Formwork: 31,000m2
·         Rebar: 35,000 Kg
·         In-situ Concrete: 820m3
·         Rock Revetment Volume: 845m3
 
 
8- Construction of Dike & Breakwater of Koohmobarak Fishing Port
 
General Information:
·         Project: Construction of Dike and Breakwater of Kohmobarak Fishing Port
·         Location: Kohmobarak Fishing port, Hormozgan Province
·         Employer: Hormozgan Fisheries Organization
·         Consultant: Sazehpardazi Iran Consulting Engineeres
·         Contractor: Karan Darya Co.
·         Implementation Period: 24 months
·         Contract Date: 28/04/2005
·         Primary Amount: 4,902,694 $
 
Technical Information:
·         Breakwater Type: Rubble Mound
·         Maine arm length: 700m
·         Secondary arm length: 430m
·         Protection Dike length: 325m
·         Access Jetty length: 444m
·         Mattress rok volume (1-50 kg): 15,419 m3
·         Core rock volume (50-250 kg): 185,469 m3
·         Filter rock volume (250-500 kg): 34,437 m3
·         Filter rock volume (500-1500 kg): 35,804 m3
·         Armour rock volume (1500-60,000 kg): 68,500 m3
·         Rock transportation: 14,492,200 km. m3
 
 
9- Construction of the Mohammad Ameri Fishing port Breakwaters
 
General Information:
·         Project: Construction of the Mohammad Ameri Fishing Port Breakwaters
·         Location: Mohammad Ameri Village, Bushehr Province  
·         Employer: Iran Fisheries Organization 
·         Consultant: Sakoo Consulting Engineers
·         Contractor: Karan Darya Co.
·         Implementation Period: 48 months
·         Contract Date: 23/03/1993
·         Expense: 4,330,259 $
 
Technical Information:
·         Breakwater Type: Rubble Mound
·         Length of main breakwater: 1,172m
·         Length of secondary breakwater: 784m
·         Base in Area: 6.5 Hectare
·         Rock Material Volume: 620,000m3 of rocks weighed 100 to 9,000 Kg
·         Construction of the Security buildings
·         site Fencing
·         Construction of access roads and asphalting
 
 
10- Rehabilitation & Construction of Rostami Fishing Port New Breakwaters
 
General Information:
·         Project:Rehabilitation & Construction of Rostami Fishing Port New Breakwaters
·         Location: 65 Km from Bushehr city
·         Employer: Iran Fisheries Stock Company 
·         Consultant: Sakoo Consulting Engineers
·         Contractor: Karan Darya Co.
·         Duration: 30 months
·         Contract Date: 14/12/2003
·         Primary expense: 5,266,322 $.
 
Technical Information:
·         Breakwater Type: Rubble Mound
·         Main arm length: 1,071 m
·         Secondary arm length: 615 m
·         Sediment dike length: 425 m
·         Basin Area: 130 hectare
·          Stone material volume: 404,000 m3
·          Special weight of stones: 2.32 ton/m3
·         Maximum weight of armor: 9 ton
·         Quarry distance: Arabi Mine at a distance of 49 Km from project location
 
 
11- Construction of Block Jetty of Rostami Fishing Port
 
General Information:
·         Project: Construction of Block Jetty of Rostami Fishing Port
·         Location: Rostami fishing port, Bushehr Province
·         Employer: Iran Fisheries Organization
·         Consultant: Sakoo Consulting Engineers
·         Contractor: Karan Darya Co.
·         Implementation Period: 24 months
·         Contract Date: 24/01/2006
·         Expense: 1,684,211 $
 
Technical Information:
·         Jetty length: 126 meters with Precast, Concrete Blocks
·         Concrete Block Volume: 3,000m3
·         Procurement and installation of Fender: 57 Pieces
·         Rock Material Volume: 5,130m3 of Rocks weighed 100 to 200Kg
·         Stone Volume behind the jetty: 27,257m3
·         Formwork: 13,250m2
·         Rebar: 65,000 Kg
·         In-situ Concrete: 1,000m3
·         Preparation and installation of 35 tone bollard: 15 pieces
·         Preparation and installation of 10 tone bollard: 26 pieces
·         Preparation and installation of Lanterns: 2 pieces
·         Preparation and installation of Geotextile: 1,653 m2
 
 
12- Construction of Basaieedu Fishing Port Jetty & Breakwater
 
General Information:
·         Project: Construction of Basaieedu Fishing Port jetty and Breakwater
·         Location: Qeshm Island
·         Employer: Iran Fisheries Stock Company
·         Consultant: Daryasazeh Consulting Engineers Co.
·         Contractor: Karan Darya Co.
·         Duration: breakwater: 27 months, jetty: 24 months
·         Contract Date: (Breakwater) 11/12/1998 (Jetty)25/08/2000 
·         Primary expense: (breakwater) 1,893,638 $. (jetty) 1,732,000 $
 
 Breakwater technical Information:
·         Breakwater Type: Rubble Mound
·         Main arm length: 900 m
·         Secondary arm length: 300 m
·         Length of Dike: 330 m
·         Basin area: 12 hectare
·         Stone material volume: 175,000 m3
·          Special weight of stones: 2.7 ton/m3
·         Maximum weight of armor: 6 ton
·         Quarry distance: 10 Km
 
Jetty technical Information:
·         Jetty type: steel sheet piles
·         Jetty length: 185 m
·         Concrete volume: 3,000 m3
·         Steel sheet piles length: 14 m and 12 m
·         Number of steel sheer piling: 600
·          Port installations: 2,000 mincluding
·         Including a 1700 m2 roofed saloon and a 300 m2 office building
  
 
13- Construction of Salakh Fishing Port Breakwater & Site Preparation
 
General Information:
·         Project: Construction of Salakh Fishing Port Breakwater & Site Preparation
·         Location: South of Qeshm Island within 75Km from Qeshm City
·         Employer: Iran Fisheries Stock Company
·         Consultant: Sazepardazi Iran Consulting Engineers
·         Contractor: Karan Darya Co.
·         Duration: breakwater: 36 months, Site preparation: 12 months
·         Contract Date: (Breakwater) 04/06/1992 (Site Preparation)15/05/1997 
·         Primary expense: 1,030,958 $
 
 Breakwater technical Information:
·         Breakwater Type: Rubble Mound
·         Length of main Arm: 910 m
·         Length of secondary Arm: 310 m
·         Basin area: 17.6 hectare
·         Stone material volume: 535,000 m3
·          Special weight of stones: 1.8 ton/m3
·         Maximum weight of armor: 5 ton
·         Quarry distance: Sarsou Mine within 60 Km from the site 
 
Landscaping technical information:
·         Earthwork volume: 19,000 m3
·          Backfilling volume: 23,700 m3
·          Asphalt area: 190,000 m2
 
 
14- Extension of Cargo & Tug Jetties (EPC)
 
General Information:
·         Project: Extension of Cargo and Tug Jetties
·         Location: Khark island, Bushehr province
·         Employer: Oil Products Exporting Terminals Co.
·         Consultant: Sazepardazi Iran Consulting Engineers
·         Contractor: Karan Darya Co.
·         Duration: 12 months
·          Contract Date : 03/02/2002
·         Joining expense: 5,234,447 $
 
Technical Information:
·         Cargo jetty Length: 106 m
·         Steel pipes diameter: 30 inch
·         Steel pipes Length: 15 m
·         Number of steel pipes: 163
·         Length of tug jetty: 144 m
·         Length of steel sheet piles: 13 & 15 m
·         Number of steel sheet piles: 119
·         Concrete volume: 5,000 m3
·         Number of cast iron bollards: 23
·         Number of Fenders: 35
·         Structural implementation: 900 m2 with electrical and mechanical installations
·         Cargo Jetty Deck: 106*20 m
·         Tug Jetty Deck: 144*20 m
·         Quay Area: 12,000 m2
·         Ligh Tower Construction: 4 towers
·         Office Building Area: 950 m2
·         Installations such as Fueling, watering & fire fighting
·         Facilities Building Area: 480 m2
·         Construction & Installation of 5 ton Rail Crane
 
 
15- Rehabilitation of Bushehr Port Commercial Jetty
 
General Information:
·         Project: Rehabilitation of Bushehr Port Commercial Jetty
·         Location: Bushehr Port
·         Employer: Ports and shipping organization of Bushehr province
·         Consultant: Sazepardazi Iran Consulting Engineers
·         Contractor: Karan Darya Company
·         Duration: 12 months
·         Contract Date: 23/09/2002
·         Expense: 652,632 $
 
Technical Information:
·         Length of the Pier: 342.2 m
·          Reinforced Concrete Demolition Volume: 300 m3
·          In situ Concrete Volume: 115 m3
·          Shotcrete Area: 1,230 m2
·         In situ Concrete Type: Low Permeable & Auto Aligned Microsilicious Concrete
·         Reinforced Concrete Demolition Method: Pneumatic hammer
·         Number of Piles: 122
·         Steel work volume: 79,130 Kg
·         Rebar work volume: 40,700 Kg
·         Formwork Area: 376 m2
 
 
16- Construction of Astara Fishing Port Breakwater & Jetty
 
General Information:
·         Project: Construction of Astara Fishing Port Breakwater and Jetty 
·         Location: Astara City, Gilan Province
·         Employer: Iran Fisheries Stock Company
·         Contractor: Karan Darya Co.
·         Duration: (breakwater) 45 months, (jetty) 18 months
·         Contract Date: (Breakwater) 26/10/1996 (jetty)12/11/2001 
·         Primary expense: 2,422,943 $
 
 Breakwater technical Information:
·         Breakwater Type: Rubble Mound
·         North main arm length: 998 m
·         South main arm length: 792 m
·         Length of secondary Arm: 325 m
·         Basin area: 17.6 hectare
·         Stone material volume: 74,0000 m3
·          Special weight of Stones: 2.5 ton/m3
·         Maximum weight of armor: 4 tons
·          Concrete volume: 7,500 m3
·         Quarry distance: Abasabad mine within 7 Km from the site
 
Jetty technical Information:
·         Jetty Type: concrete sheet piles
·         Length of jetty: 127 m
·         Volume of concrete: 4,500 m3
·         Length of concrete sheet piles: 16 m
·         Number of piles: 340
·          Jetty shading structure area: 480 m2
 
 
17- Rehabilitation & Elongation of Breakwater, Construction Of Jetty,
Access Road & Police Building of Bolkheir Port
 
General Information:
·         Project: Rehabilitation & Elongation of Breakwater, Construction of Jetty, Access Road & Police Building of Bolkheir port
·         Location: Bolkheir Fishing Port, Bushehr Province  
·         Employer: Iran Fisheries Organization
·         Consultant: Sazepardazi Iran Consulting Engineers
·         Contractor: Karan Darya Co.
·         Implementation Period: 15 months
·         Contract Date: 07/03/2005
·         Expense: 2,434,926 $
 
Technical Information:
·         Length of the pier: 50 meters with precast concrete blocks
·         Concrete Block Volume: 1,287m3
·         Dredging work: 2,361m3
·         Stone Volume: 65,257 m3of rocks weighed 1 to 2,300 kg
·         Formwork: 5,500m2
·         In-situ Concrete: 300m3
·         Access Road: 500m
·         Construction of the Police Building: 120m2
·         Procurement & Installation of Stopper: 67 m
·         Procurement & Installation of Fenders: 16 pieces
·         Procurement & Installation of Bollards: 5 pieces
 
 
18- Construction & Rehabilitation of the Roads of Siri Island
 
General Information:
·         Project: Construction and Rehabilitation of the Roads of Siri Island
·         Location: Siri Island, Hormozgan Province
·         Employer: National Iranian Oil Company _ Iranian Offshore Oil Co.
·         Consultant: Engineering Department of Iranian Offshore Oil Co. 
·         Contractor: Karan Darya Co.
·         Implementation Period: 16 months
·         Contract Date: 01/08/1998
·         Expense: 1,216,880 $
 
Technical Information:
·         Excavation: 36,500m3
·         Back filling: 21,200m3
·         Sub grade Material Volume:24,000 m3
·         Asphalt: 11Km
·         Spreading and Leveling: 264,000m2
 
 
19- Construction of 9.5 Km of Khark Island Roads
 
General Information:
·         Project: Construction of 9.5 Km of the Khark Island Road
·         Location: Khark Island, Bushehr Province
·         Employer: Khark General Operation Management
·         Consultant: Gozineh Consulting Engineers  
·         Contractor: Karan Darya Co.
·         Implementation Period: 18 months
·         Contract Date: 02/04/2004
·         Expense: 4,315,789 $
 
Technical Information:
·         Construction 9.5 Kilometers roads with 25 meters width including Two 7/5m bands
·         6m of Road shoulder( 3m in each side ) and tabulation of 4 meters distance between two bands.
·         Bridges and channels in type of jointed weighted concrete that has been implemented in different spans in form of precast slabs including: 477m3 Lean Concrete, 1,427m3 concrete with 250Kg cement content, 190 m3 concrete with 350Kg cement content and 512 m3 concrete with 350Kg cement content for precast parts
·         Total volume of soil operations about 350,000m3 including: excavation and earth filling on the road track surface asphalt thickness is about 12 cm that includes 7cm binder course and 5Cm Toopka Course
 
 
20- Construction of foundations & Mechanical installation
Of urea & Ammonia Tanks of Asalouyeh
 
General Information:
·         Project: Construction of foundations and Mechanical installation Of urea & Ammonia Tanks of Asalouyeh
·         Location: South Pars Economic Special Zone
·         Employer: petrochemical Industries development management 
·         Consultant: Petrochemical Industries Engineering and Designing Company
·         Contractor: Karan Darya Co.
·         Duration: 10 months
·         Contract Date: 08/04/2002
·         Primary expense: 1,375,789 $
 
Technical Information:
·          Earthworks volume: 10,000m3
·         Concrete volume: 11,000m3
·          Formwork area:6000m2
·         Shattering: 6,000m2
·         Prefabricated steel structure Weight: 2,000 ton
·         Sandwich panel cover Installation: 38,000m2
·         Grouting: 12,000 litres
·         Consumed metal bars Weight: 850 tons
 
 
21- Assaluyeh Welfare Services Center
 
General Information:
·         Project: Assaluyeh Welfare Services Center
·         Location: Pars Economic Special Zone
·         Employer: Oil Development Engineering Co.
·         Consultant: Mandan Consulting Engineers
·         Contractor: Karan Darya Co.
·         Duration: 22 months
·         Contract Date: 20/05/1996
·         Primary expense: 2,759,789 $
 
Technical Information:
·         Structure type: steel structure with cement rendering facade 
·         Built-up area: 6,700mincluding 3 buildings
·          Earthworks volume: 150,000 m3
·         Concrete volume: 3,750 m3
·         Landscaping: street: 3.5Km of street
·          Volume of Aerial & ground tanks: 1,150 m3
·         Pool Construction volume: 680 m3
 
 
22- Southern Road of Coastal Traffic Area in Shahid Rajae Port
 
General Information:
·         Project: Southern Road of Coastal Traffic Area in Shahid Rajae Port
·         Location: special economic zone of Shahid Rajae Port, Hormozgan Province
·         Employer: Shipping and Ports Organization of the Hormozgan province 
·         Consultant: Tadbir Sahel Pars Consulting Engineers
·         Contractor: Karan Darya Co.
·         Implementation Period: 12 months
·         Contract Date: 27/04/2006
·         Expense: 2,436,316 $
 
Technical Information:
·         Construction of shading structure: 900m2 Construction of concrete channel 
·         Excavation: 16,000m3
·          Backfilling: 43,000m3
·          Rock masonry: 1,800m3
·         In-situ concrete: 5,000m3
·         Precast concrete: 1,200m3
·         Formwork: 14,000m3
·         Rebar work Area: 430,000 Kg
·         Asphalting : 15,000 ton in 3 layers.

 

 