 Incompleted Projects 

Project Name
Double Wall Gas Tanks - South Pars Gas Field Development Phases 17 and 18 - EPC
Client
IPMI
Client Consultant
Tehran Raymand Co.
Contractor Consultant
WEIR LGE
Contractor Name
Panahsaz Iran Eng. Co.
Contract Duration
33 Months
Location
Asaluyeh, Bushehr Province, Iran
Contract Ratification Date
October 2008
Contract Completion Date
Ongoing
Project Outlay (Euro)
43, 200, 000

 
Project Name
Double Wall Gas Tanks - South Pars Gas Field Development Phases 15 and 16 - EPC
Client
Sepanir Oil and Gas Energy Eng. Co.
Client Consultant
Narghan and Sazeh Co.
Contractor Consultant
WEIR LGE
Contractor Name
Panahsaz Iran Eng. Co.
Contract Duration
30 Months
Location
Asaluyeh, Bushehr Province, Iran
Contract Ratification Date
October 2007
Contract Completion Date
Ongoing
Project Outlay (Euro)
45, 600, 000
  

Project Name
Double Wall Gas Tanks – Kharg Island - EPC
Client
Iritec
Contractor Name
Panahsaz Iran Eng. Co.
Contract Duration
28 Months
Location
Kharg , Bushehr Province , Iran
Contract Completion Date
Ongoing

  
Project Name
Double Wall LPG Tanks - Sirri NGL - EPC
Client
OIEC
Contractor Name
Panahsaz Iran Eng. Co.
Contract Duration
23 Months
Location
Sirri, Hormozghan Province, Iran
Contract Completion Date
Ongoing
 

Project Name
Design and Construction of Sewage Treatment Plant of Shahr-e-Ghods - EPC
Client
Tehran Province Water and Wastewater Co.
Consultant
Lar Eng. Consultant Co.
Contract Type
Constructive
Contractor Name
Panahsaz Iran Eng. Co.
Location
Tehran Province, Iran
Contract Ratification Date
May 2007
Contract Completion Date
Ongoing
Project Outlay (Million Rial)
98, 673

 
Project Name
Construction and Electrical Installation of Parrehsar Water Intake system Combinational Cycle Power Plant
Client
MAPNA Group
Consultant
Sazeh Pardazi Iran Eng. Consultant Co.
Contract Type
Non-constructive
Contractor Name
Panahsaz Iran Eng. Co.
Location
36 Km of Anzali Road, Gilan Province, Iran
Contract Ratification Date
February 2008
Contract Completion Date
Ongoing
Project Outlay (Million Rial)
229, 760
 
 
 

Project Name
Construction of Buildings and Civil Operations of Sirri NGL Project
Client
OIEC
Contract Type
Non-constructive
Contractor Name
Panahsaz Iran Eng. Co.
Location
Sirri, Hormozgan Province, Iran
Contract Ratification Date
December 2006
Contract Completion Date
Ongoing
Project Outlay (Million Rial)
173, 491

 
Project Name
Construction of 4 building complex
Client
Koshapaydar
Contract Type
Non-constructive
Contractor Name
Panahsaz Iran Eng. Co.
Location
Tehran Province, Iran
Contract Ratification Date
May 2010
Contract Completion Date
Ongoing
Project Outlay (Million Rial)
240,000
 
 
Project Name
Construction of pump station, pipe lain
Client
Jahad kehsavrzi ardabil
Contract Type
constructive
Contractor Name
Panahsaz Iran Eng. Co.
Location
Ardabil Province, Iran
Contract Ratification Date
July 2010
Contract Completion Date
Ongoing
Project Outlay (Million Rial)
7,836
  

Project Name
Construction of  Shadegan port
Client
Ports & Maritime Head Quarters of khozestan Pravince
Contract Type
Non-constructive
Contractor Name
Panahsaz Iran Eng. Co.
Location
Khozestan Province, Iran
Contract Ratification Date
May 2010
Contract Completion Date
Ongoing
Project Outlay (Million Rial)
63, 500

 

 

 